Committee chairman Mas Ermieyati Samsudin says Lunas must bear the cost of redoing work and replacing ageing parts in the navy ship project.Committee chairman Mas Ermieyati Samsudin says Lunas must bear the cost of redoing work and replacing ageing parts in the navy ship project.

No extra funds for LCS project, cost must stay under RM11.22bil, says PAC

이 콘텐츠에 대한 의견이나 우려 사항이 있으시면 [email protected]으로 연락주시기 바랍니다
PAC chairman Mas Ermieyati Samsudin said the LCS project delay was mainly due to a technical audit by France’s Naval Group, which required work to be redone on nearly 4,000 items. (Bernama pic)

KUALA LUMPUR: The Public Accounts Committee (PAC) says the cost of the littoral combat ship (LCS) project must not exceed its RM11.22 billion ceiling and that no additional government funds should be allocated for redoing work or replacing ageing parts.

PAC chairman Mas Ermieyati Samsudin said the committee had recommended that the defence and finance ministries keep tight control over spending to ensure that the troubled navy project does not exceed the approved cost ceiling.

“The total contract cost remains fixed at RM11.22 billion,” she said at a press conference in Parliament today.

Mas Ermieyati said the government was using an earned value management system, with payments made only for verified physical work.

She said this replaced the previous milestone payment system, which exposed the project to the risk of overpayment.

PAC said the project’s overall physical progress stood at 75.73% as of December last year, while the first ship, LCS-1, was 82.90% complete.

LCS-1 underwent its first sea trial on Jan 28, reaching a speed of seven knots, but its delivery has been pushed back to December, four months later than planned.

LCS-2 is now expected to be delivered in August 2027, while the delivery schedule for LCS-3 to LCS-5 remains unchanged, with the final ship due by April 2029.

Defence minister Khaled Nordin previously told Parliament that Norway’s cancellation of the naval strike missile export licence would not affect the LCS delivery schedule, which had been guaranteed by Lumut Naval Shipyard Sdn Bhd (Lunas), the company building the ships.

Khaled said the LCS still had other capabilities, including anti-submarine, anti-air and electronic warfare, as well as a combat management system that integrated these capabilities with the ship’s radar and sensors.

Mas Ermieyati said the LCS project delay was mainly due to a technical audit by France’s Naval Group, which required work to be redone on nearly 4,000 items.

She said 170 major LCS systems still required testing, while some European original equipment manufacturers had gone bankrupt after the Covid-19 pandemic, forcing the contractor to find other vendors and go through fresh certification.

Mas Ermieyati said PAC also recommended that the defence ministry and the navy submit written progress reports to the committee every three months, and that Lunas maintain sufficient stocks of critical items to avoid further delays caused by issues with foreign vendors.

시장 기회
Massa 로고
Massa 가격(MAS)
$0.00321
$0.00321$0.00321
0.00%
USD
Massa (MAS) 실시간 가격 차트

World Cup Combo: Aim for 200x

World Cup Combo: Aim for 200xWorld Cup Combo: Aim for 200x

Combine up to 20 World Cup matches in one order

면책 조항: 본 사이트에 재게시된 글들은 공개 플랫폼에서 가져온 것으로 정보 제공 목적으로만 제공됩니다. 이는 반드시 MEXC의 견해를 반영하는 것은 아닙니다. 모든 권리는 원저자에게 있습니다. 제3자의 권리를 침해하는 콘텐츠가 있다고 판단될 경우, [email protected]으로 연락하여 삭제 요청을 해주시기 바랍니다. MEXC는 콘텐츠의 정확성, 완전성 또는 시의적절성에 대해 어떠한 보증도 하지 않으며, 제공된 정보에 기반하여 취해진 어떠한 조치에 대해서도 책임을 지지 않습니다. 본 콘텐츠는 금융, 법률 또는 기타 전문적인 조언을 구성하지 않으며, MEXC의 추천이나 보증으로 간주되어서는 안 됩니다.

$5M in SPCX Positions for Free

$5M in SPCX Positions for Free$5M in SPCX Positions for Free

0 fees, 100x leverage, daily prizes, 7K+ stocks/ETFs