KUALA LUMPUR, June 24 — The New Pantai Expressway Extension Project (NPE 2) will use a barrier-free toll collectio...KUALA LUMPUR, June 24 — The New Pantai Expressway Extension Project (NPE 2) will use a barrier-free toll collectio...

RM1.7b NPE 2 to feature barrier-free MLFF toll system to ease Klang Valley congestion

2026/06/24 16:02
2 min read
For feedback or concerns regarding this content, please contact us at [email protected]

KUALA LUMPUR, June 24 — The New Pantai Expressway Extension Project (NPE 2) will use a barrier-free toll collection system or Multi-Lane Free Flow (MLFF) when fully completed to reduce traffic congestion, especially during peak hours.

IJM Corporation Berhad (IJM) Toll Division chief executive officer Chua Lay Hoon said the project, which is expected to be fully completed in 2029, involves a main route of 6.4 kilometres (km) or 15 km in total, including a ramp from the Pantai Dalam Toll Plaza to Jalan Istana here.

“If the MLFF has not been implemented after this project is completed, the transition to another toll system can be done with changes to the toll collection equipment without requiring major modifications,” she said at a special briefing on the NPE 2 Extension Project with the media here today.

She said the project, worth RM1.7 billion, is currently at about six per cent, which includes design and modelling work with physical work at the construction site starting last month.

Chua said the highway extension project would strengthen the integrated highway network in the Klang Valley through better connectivity between the NPE, the Sungai Besi Expressway (BESRAYA) and the proposed Istana-Kiara Expressway (LIKE) in line with the aspirations of the Kuala Lumpur Traffic Master Plan 2040.

Commenting on traffic management during the construction work, Chua said a comprehensive Traffic Management Plan (TMP) would be implemented throughout the period to ensure smooth traffic flow and safety of road users.

“Among the measures that would be implemented include real-time traffic monitoring, coordination with relevant agencies, scheduled road closures and diversions that would only be carried out during off-peak hours or at night, as well as the provision of a dedicated traffic management team.

“The safety of road users, construction workers and nearby communities remains a priority throughout the construction period while minimising disruption to highway users,” she said. — Bernama 

CHZ +28%! Will History Repeat?

CHZ +28%! Will History Repeat?CHZ +28%! Will History Repeat?

0-fee opening long & short. Be ready for any move!

Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact [email protected] for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.

World Cup Combo: Aim for 200x

World Cup Combo: Aim for 200xWorld Cup Combo: Aim for 200x

Combine up to 20 World Cup matches in one order